Sec. 88.3. Exhibit E-3: underground construction
Latest version.
- If any portion of the proposed transmission line is to be built underground, the applicant shall:(a) indicate the type of cable system to be used;(b) provide the design standards for that system;(c) indicate the number and size of conductors to be used; and(d) indicate, on a profile of the line:(1) the depth of the cable; and(2) the location of oil pumping stations and manholes.