Sec. 88.3. Exhibit E-3: underground construction  


Latest version.
  • If any portion of the proposed transmission line is to be built underground, the applicant shall:
    (a) indicate the type of cable system to be used;
    (b) provide the design standards for that system;
    (c) indicate the number and size of conductors to be used; and
    (d) indicate, on a profile of the line:
    (1) the depth of the cable; and
    (2) the location of oil pumping stations and manholes.