New York Codes Rules Regulations (Last Updated: March 27,2024) |
TITLE 16. Department of Public Service |
Chapter III. Gas Utilities |
Subchapter A. Service |
Part 228. Testing Gas Meters on Complaint of Customers |
Sec. 228.2. Requirements for referee test
Latest version.
- Whenever any utility receives notice from this commission that a customer has requested a referee test of his/her gas meter, the utility shall replace the meter within 10 days unless it is of a type usually tested in the field. In the latter case, the utility shall provide appropriate personnel and equipment to assist in the field-testing of the accuracy of the meter by this commission. If a meter cannot be made available for a referee test within the time specified, written notice shall be sent to this commission giving the causes for the delay.