Sec. 900-8.1. Publication of draft siting permit  


Latest version.
  • (a) No later than 60 days following the date upon which an application has been deemed complete, and following consultation with any relevant State agency or authority, the ORES shall publish on its website for public comment draft permit conditions prepared by the office or a statement of intent to deny.
    (b) No later than 60 days following the date upon which an application has been deemed complete, a combined notice of availability of draft permit conditions or statement of intent to deny, public comment period and public comment hearing, and issues determination, as defined in section 900-8.2(d) of this Subpart, shall be published on the ORES website.