2/14/07 N.Y. St. Reg. PSC-38-06-00011-A
PURSUANT TO THE PROVISIONS OF THE State Administrative Procedure Act, NOTICE is hereby given of the following proposed rule:
Proposed action:
The commission, on Jan. 17, 2007, adopted an order in Case 06-E-1048 approving the petition filed by ADD Development & Management to submeter electricity at 3 Care Lane, Saratoga Springs, NY.
Statutory authority:
Public Service Law, sections 2, 4(1), 65(1), 66(1), and 67(1)
Subject:
Petition for the submetering of electricity.
Purpose:
To grant the request of ADD Development & Management to submeter electricity at 3 Care Lane, Saratoga Springs, NY.
Substance of proposed rule:
The Commission approved a request by ADD Development & Management, to submeter electricity at 3 Care Lane, Saratoga Springs, New York, located in the territory of National Grid Corporation.
Text of proposed rule and any required statements and analyses may be obtained by filing a Document Request Form (F-96) located on our website http://www.dps.state.ny.us/f96dir.htm. For questions, contact:
Central Operations, Public Service Commission, Bldg. 3, Empire State Plaza, Albany, NY 12223-1350, (518) 474-2500
Data, views or arguments may be submitted to:
Jaclyn A. Brilling, Secretary, Public Service Commission, Bldg. 3, Empire State Plaza, Albany, NY 12223-1350, (518) 474-6530
Public comment will be received until:
45 days after publication of this notice.
Regulatory Impact Statement, Regulatory Flexibility Analysis, Rural Area Flexibility Analysis and Job Impact Statement
Statements and analyses are not submitted with this notice because the proposed rule is within the definition contained in section 102(2)(a)(ii) of the State Administrative Procedure Act.