PURSUANT TO THE PROVISIONS OF THE State Administrative Procedure Act, NOTICE is hereby given of the following action:
Action taken:
The commission, on April 23, 2008, adopted an order regarding Consolidated Edison Company of New York, Inc.'s report on Rider U—Distribution Load Relief Program pursuant to commission order in Case 07-E-0392, issued June 21, 2007.
Statutory authority:
Public Service Law, section 66(12)
Subject:
Report on Rider U—Distribution Load Relief Program (Rider U).
Purpose:
To approve with modifications the report assessing the effectiveness of the Rider U Program changes on increasing the level of customer participation.
Substance of final rule:
The Public Service Commission adopted an order regarding Consolidated Edison Company of New York, Inc.'s report on Rider U—Distribution Load Relief Program pursuant to Commission Order in Case 07-E-0392, issued June 21, 2007, and directed the company to make several changes to be implemented for the summer 2008 capability period, subject to the terms and conditions set forth in the order.
Final rule compared with proposed rule:
No changes.
Text of rule may be obtained from:
Central Operations, Public Service Commission, Bldg. 3, 14th Fl., Empire State Plaza, Albany, NY 12223-1350, by fax to (518) 474-9842, by calling (518) 474-2500. An IRS employer ID no. or social security no. is required from firms or persons to be billed 25 cents per page. Please use tracking number found on last line of notice in requests.
Assessment of Public Comment
An assessment of public comment is not submitted with this notice because the rule is within the definition contained in section 102(2)(a)(ii) of the State Administrative Procedure Act.