PSC-20-12-00007-P Con Edison's Report on 2011 Performance Under Electric Service Reliability Performance Mechanism  

  • 5/16/12 N.Y. St. Reg. PSC-20-12-00007-P
    NEW YORK STATE REGISTER
    VOLUME XXXIV, ISSUE 20
    May 16, 2012
    RULE MAKING ACTIVITIES
    PUBLIC SERVICE COMMISSION
    PROPOSED RULE MAKING
    NO HEARING(S) SCHEDULED
     
    I.D No. PSC-20-12-00007-P
    Con Edison's Report on 2011 Performance Under Electric Service Reliability Performance Mechanism
    PURSUANT TO THE PROVISIONS OF THE State Administrative Procedure Act, NOTICE is hereby given of the following proposed rule:
    Proposed Action:
    The Public Service Commission is considering whether Consolidated Edison Company of New York, Inc. (Con Edison) met its 2011 performance standards under the Electric Service Reliability Performance Mechanism.
    Statutory authority:
    Public Service Law, sections 65 and 66
    Subject:
    Con Edison's Report on 2011 Performance under Electric Service Reliability Performance Mechanism.
    Purpose:
    To consider whether Con Edison has met its performance standards as prescribed by the Commission in Con Edison's rate plan.
    Substance of proposed rule:
    The Public Service Commission (Commission) is considering whether to adopt, in whole or in part, to reject, or to take any other action with respect to Consolidated Edison Company of New York, Inc. (Con Edison) Report on 2011 Performance under Electric Service Reliability Performance Mechanism (2011 RPM Report). Specifically, the Commission will consider whether Con Edison has met all of the required performance standards set forth in the utility's rate plan. Con Edison states that a revenue adjustment of $9 million is not applicable for its failure to meet its network duration and network outages per 1000 customers threshold standards given that interruptions were caused by excludable overhead major storms that have impacted its network system. In addition, Con Edison states that a revenue adjustment of $5 million is not applicable for its failure to meet its radial duration threshold standard due to outages beyond its control. The utility states that it has met all the remaining performance metrics, which includes the radial frequency threshold standards, summer network feeder open automatics, major outages, radial restoration, pole repairs, shunt removals, no current streetlight and traffic signal repairs, remote monitoring system and over duty circuit breaker replacements.
    Text of proposed rule and any required statements and analyses may be obtained by filing a Document Request Form (F-96) located on our website http://www.dps.state.ny.us/f96dir.htm. For questions, contact:
    Leann Ayer, Public Service Commission, 3 Empire State Plaza, Albany, New York 12223-1350, (518) 486-2655, email: leann.ayer@dps.ny.gov
    Data, views or arguments may be submitted to:
    Jaclyn A. Brilling, Secretary, Public Service Commission, 3 Empire State Plaza, Albany, New York 12223-1350, (518) 474-6530, email: Secretary@dps.ny.gov
    Public comment will be received until:
    45 days after publication of this notice.
    Regulatory Impact Statement, Regulatory Flexibility Analysis, Rural Area Flexibility Analysis and Job Impact Statement
    Statements and analyses are not submitted with this notice because the proposed rule is within the definition contained in section 102(2)(a)(ii) of the State Administrative Procedure Act.
    (09-E-0428SP4)

Document Information