6/3/09 N.Y. St. Reg. PSC-02-09-00011-A
PURSUANT TO THE PROVISIONS OF THE State Administrative Procedure Act, NOTICE is hereby given of the following action:
Action taken:
On 5/14/09 the PSC adopted an order approving, the request of Long Island Power Authority to waive several filing requirements in connection with an Article VII application.
Statutory authority:
Public Service Law, section 122(1)
Subject:
Waiver of filing requirements.
Purpose:
To approve waivers for a Certificate of Environmental Compatibility & Public Need to install an electric transmission facility.
Substance of final rule:
The Commission, on May 14, 2009, adopted an order approving the request of Long Island Power Authority to waive several filing requirements in connection with its application for a Certificate of Environmental Compatibility and Public Need to install a 138 kV electric transmission facility in an existing conduit, subject to the terms and conditions set forth in the order.
Final rule as compared with last published rule:
No changes.
Text of rule may be obtained from:
Leann Ayer, Public Service Commission, 3 Empire State Plaza, Albany, New York 12223-1350, (518) 486-2655, email:
leann_ayer@dps.state.ny.us An IRS employer ID no. or social security no. is required from firms or persons to be billed 25 cents per page. Please use tracking number found on last line of notice in requests.
Assessment of Public Comment
An assessment of public comment is not submitted with this notice because the rule is within the definition contained in section 102(2)(a)(ii) of the State Administrative Procedure Act.