PSC-22-09-00011-P Cost Allocation for Consolidated Edison's East River Repowering Project  

  • 6/3/09 N.Y. St. Reg. PSC-22-09-00011-P
    NEW YORK STATE REGISTER
    VOLUME XXXI, ISSUE 22
    June 03, 2009
    RULE MAKING ACTIVITIES
    PUBLIC SERVICE COMMISSION
    PROPOSED RULE MAKING
    NO HEARING(S) SCHEDULED
     
    I.D No. PSC-22-09-00011-P
    Cost Allocation for Consolidated Edison's East River Repowering Project
    PURSUANT TO THE PROVISIONS OF THE State Administrative Procedure Act, NOTICE is hereby given of the following proposed rule:
    Proposed Action:
    The Commission is considering examining the allocation of costs of Consolidated Edison Company of New York, Inc.'s East River Repowering Project, between electric revenue requirements and steam revenue requirements.
    Statutory authority:
    Public Service Law, sections 65, 66, 79, 80 and 81
    Subject:
    Cost allocation for Consolidated Edison's East River Repowering Project.
    Purpose:
    To determine whether any changes are warranted in the cost allocation of Consolidated Edison's East River Repowering Project.
    Substance of proposed rule:
    The Commission has initiated a proceeding to examine, among other things, the allocation of costs of Consolidated Edison Company of New York, Inc.’s (Consolidated Edison) East River Repowering Project, between electric revenue requirements and steam revenue requirements. On May 7, 2009, Consolidated Edison filed an East River Repowering Project Cost Allocation Study that recommends continuation of the “incremental method” of allocation that is currently in use. The Cost Allocation Study also presents a comparison of results using different fuel cost allocation methods. The proceeding will examine the Cost Allocation Study, including the alternative allocation methods presented in the Study as well as other, related, alternative methods presented by other parties within the proceeding. Potential actions of the Commission are to continue the current allocation method, or to order the use of a different allocation method, effective not sooner than October 1, 2010. The Commission may also adopt rate mitigation options or other measures related to the issues presented by the Cost Allocation Study.
    Text of proposed rule and any required statements and analyses may be obtained by filing a Document Request Form (F-96) located on our website http://www.dps.state.ny.us/f96dir.htm. For questions, contact:
    Leann Ayer, Public Service Commission, 3 Empire State Plaza, Albany, New York 12223-1350, (518) 486-2655, email: leann_ayer@dps.state.ny.us
    Data, views or arguments may be submitted to:
    Jaclyn A. Brilling, Secretary, Public Service Commission, 3 Empire State Plaza, Albany, New York 12223-1350, (518) 474-6530, email: jaclyn_brilling@dps.state.ny.us
    Public comment will be received until:
    45 days after publication of this notice.
    Regulatory Impact Statement, Regulatory Flexibility Analysis, Rural Area Flexibility Analysis and Job Impact Statement
    Statements and analyses are not submitted with this notice because the proposed rule is within the definition contained in section 102(2)(a)(ii) of the State Administrative Procedure Act.
    (09-S-0029SP3)

Document Information