6/8/16 N.Y. St. Reg. PSC-10-16-00013-A
PURSUANT TO THE PROVISIONS OF THE State Administrative Procedure Act, NOTICE is hereby given of the following action:
Action taken:
On 5/19/16, the PSC adopted an order approving New York State Electric and Gas Corporation's (NYSEG) amendments to Dynamic Load Management (DLM) Programs, contained in P.S.C. No. 120 — Electricity.
Statutory authority:
Public Service Law, sections 65 and 66
Subject:
Amendments to DLM Programs, contained in P.S.C. No. 120 — Electricity.
Purpose:
To approve NYSEG's amendments to DLM Programs, contained in P.S.C. No. 120 — Electricity.
Substance of final rule:
The Commission, on May 19, 2016, adopted an order approving New York State Electric and Gas Corporation's amendments to Dynamic Load Management Programs, contained in P.S.C. No. 120 – Electricity, and directed the company to file further revisions to effectuate the changes, subject to the terms and conditions set forth in the order.
Final rule as compared with last published rule:
No changes.
Text of rule may be obtained from:
John Pitucci, Public Service Commission, Three Empire State Plaza, Albany, New York 12223, (518) 486-2655, email:
john.pitucci@dps.ny.gov An IRS employer ID no. or social security no. is required from firms or persons to be billed 25 cents per page. Please use tracking number found on last line of notice in requests.
Assessment of Public Comment
An assessment of public comment is not submitted with this notice because the rule is within the definition contained in section 102(2)(a)(ii) of the State Administrative Procedure Act.