PSC-35-08-00016-P Transition Cost Surcharge  

  • 8/27/08 N.Y. St. Reg. PSC-35-08-00016-P
    NEW YORK STATE REGISTER
    VOLUME XXX, ISSUE 35
    August 27, 2008
    RULE MAKING ACTIVITIES
    PUBLIC SERVICE COMMISSION
    PROPOSED RULE MAKING
    NO HEARING(S) SCHEDULED
     
    I.D No. PSC-35-08-00016-P
    Transition Cost Surcharge
    PURSUANT TO THE PROVISIONS OF THE State Administrative Procedure Act, NOTICE is hereby given of the following proposed rule:
    Proposed Action:
    The Commission is considering a proposal filed by Rochester Gas & Electric Corporation (RG&E) to revise its Transition Cost Surcharge.
    Statutory authority:
    Public Service Law, section 66(12)
    Subject:
    Transition Cost Surcharge.
    Purpose:
    To make revisions to RG&E's Transition Cost Surcharge.
    Substance of proposed rule:
    The Commission is considering a proposal filed by Rochester Gas & Electric Corporation (RG & E) to eliminate the transition costs associated with ANR Pipeline Company (ANR) and Great Lakes Pipeline Company (Great Lakes) storage assets from its Transition Costs Surcharge. RG & E is making its proposal since it will no longer hold pipeline and storage contracts on ANR and Great Lakes pipelines upon the expiration of the contracts on October 31, 2008. The Commission may approve, reject or modify, in whole or in part, RG & E's proposal.
    Text of proposed rule and any required statements and analyses may be obtained by filing a Document Request Form (F-96) located on our website http://www.dps.state.ny.us/f96dir.htm. For questions, contact:
    Leann Ayer, Public Service Commission, 3 Empire State Plaza, Albany, New York 12223-1350, (518) 486-2655, email: Leann_Ayer@DPS. state.ny.us
    Data, views or arguments may be submitted to:
    Jaclyn A. Brilling, Secretary, Public Service Commission, 3 Empire State Plaza, Albany, New York 12223-1350, (518) 474-6530, email: Jaclyn_Brilling@DPS.state.ny.us
    Public comment will be received until:
    45 days after publication of this notice.
    Regulatory Impact Statement, Regulatory Flexibility Analysis, Rural Area Flexibility Analysis and Job Impact Statement
    Statements and analyses are not submitted with this notice because the proposed rule is within the definition contained in section 102(2)(a)(ii) of the State Administrative Procedure Act.
    (08-G-0889SA1)

Document Information