PSC-16-11-00007-A Transfer of Ownership of a Generation Facility and Gas Pipeline from Standard to Alliance  

  • 8/3/11 N.Y. St. Reg. PSC-16-11-00007-A
    NEW YORK STATE REGISTER
    VOLUME XXXIII, ISSUE 31
    August 03, 2011
    RULE MAKING ACTIVITIES
    PUBLIC SERVICE COMMISSION
    NOTICE OF ADOPTION
     
    I.D No. PSC-16-11-00007-A
    Filing Date. Jul. 18, 2011
    Effective Date. Jul. 18, 2011
    Transfer of Ownership of a Generation Facility and Gas Pipeline from Standard to Alliance
    PURSUANT TO THE PROVISIONS OF THE State Administrative Procedure Act, NOTICE is hereby given of the following action:
    Action taken:
    On 7/14/11, the PSC adopted an order approving the petition of Standard Power LLC and Alliance Energy, New York for the transfer of ownership interests in a 50 MW electric generating facility and a gas pipeline used to fuel the facility located in Binghamton.
    Statutory authority:
    Public Service Law, sections 2(11), 5(1)(b) and 70
    Subject:
    Transfer of ownership of a generation facility and gas pipeline from Standard to Alliance.
    Purpose:
    To approve the transfer of ownership of a generation facility and gas pipeline from Standard to Alliance.
    Substance of final rule:
    The Commission, on July 14, 2011 adopted an order approving the petition of Standard Power LLC and Alliance Energy, New York for the transfer of ownership interests in Standard Binghamton LLC from Standard Power LLC to Alliance Energy, New York. Standard Binghamton owns and operates a 50 MW electric generating facility and a gas pipeline used to fuel the facility located in Binghamton and will continue as the direct owner after consummation of the transaction, subject to the terms and conditions set forth in the order.
    Final rule as compared with last published rule:
    No changes.
    Text of rule may be obtained from:
    Leann Ayer, Public Service Commission, Three Empire State Plaza, Albany, New York 12223, (518) 486-2655, email: leann_ayer@dps.state.ny.us An IRS employer ID no. or social security no. is required from firms or persons to be billed 25 cents per page. Please use tracking number found on last line of notice in requests.
    Assessment of Public Comment
    An assessment of public comment is not submitted with this notice because the rule is within the definition contained in section 102(2)(a)(ii) of the State Administrative Procedure Act.
    (11-M-0117SA1)

Document Information

Effective Date:
7/18/2011
Publish Date:
08/03/2011