    PURSUANT TO THE PROVISIONS OF THE State Administrative Procedure Act, NOTICE is hereby given of the following action:
    Action taken:
    On August 20, 2008, the PSC adopted an order approving a petition by Linden Plaza Preservation LP, to submeter electricity at Linden Plaza, Brooklyn, New York.
    Statutory authority:
    Public Service Law, sections 2, 4(1), 65(1), 66(1), (2), (3), (4), (12) and (14)
    Subject:
    Petition for the submetering of electricity.
    Purpose:
    To grant the petition of Linden Plaza Preservation LP, to submeter electricity at Linden Plaza, Brooklyn, New York.
    Substance of final rule:
    The Commission, on August 20, 2008, adopted an order approving a petition by Linden Plaza Preservation LP, to submeter electricity at Linden Plaza, Brooklyn, New York, located in the territory of Consolidated Edison Company of New York, Inc.
    Final rule as compared with last published rule:
    No changes.
    Text of rule may be obtained from:
    Leann Ayer, Public Service Commission, Three Empire State Plaza, Albany, New York 12223, (518) 486-2655, email: leann_ayer@dps. state.ny.us
    Assessment of Public Comment
    An assessment of public comment is not submitted with this notice because the rule is within the definition contained in section 102(2)(a)(ii) of the State Administrative Procedure Act.
    (08-E-0433SA1)

Document Information

Effective Date:
8/27/2008
Publish Date:
09/17/2008