5/13/09 N.Y. St. Reg. PSC-08-09-00004-A
PURSUANT TO THE PROVISIONS OF THE State Administrative Procedure Act, NOTICE is hereby given of the following action:
Action taken:
On 4/7/09, the PSC adopted an order approving the joint petition of EPCOR Power LLC, EPCOR Power Enterprises LLC, and Castleton Energy Center LLC, to transfer ownership interests to Castleton Energy, of EPCOR Castleton in a 67 MW generation facility.
Statutory authority:
Public Service Law, section 70
Subject:
To transfer ownership interests in a 67 MW generation facility.
Purpose:
To approve the transfer ownership interests in a 67 MW generation facility.
Substance of final rule:
The Commission, on April 21, 2009, adopted an order approving the joint petition of EPCOR Power LLC, EPCOR Power Enterprises LLC, and Castleton Energy Center LLC, to transfer ownership interests to Castleton Energy, of EPCOR Castleton for a 67 MW gas-fired generation facility located in Castleton-on-Hudson, New York, subject to the terms and conditions set forth in the order.
Final rule as compared with last published rule:
No changes.
Text of rule may be obtained from:
Leann Ayer, Public Service Commission, Three Empire State Plaza, Albany, New York 12223, (518) 486-2655, email:
leann_ayer@dps.state.ny.us An IRS employer ID no. or social security no. is required from firms or persons to be billed 25 cents per page. Please use tracking number found on last line of notice in requests.
Assessment of Public Comment
An assessment of public comment is not submitted with this notice because the rule is within the definition contained in section 102(2)(a)(ii) of the State Administrative Procedure Act.